The planning phase uses the floor plans to find preliminary installation points for TBRs/TMEs.
Generic simplified schema | Real floorplan |
Draw a grid with horizontal and vertical lines at a distance of 30 m to the preliminary TME and TBR locations, starting in the top left corner of the floor plan. Start the grid 15 m from the building walls and continue to draw a grid of 30 m x 30 m squares.
Review the floor plan and identify any possible obstacles, e.g. elevator shafts, concrete walls, vending machines, staircases, etc.. Mark any large obstacles on the floor plan.
Decide in advance where to install TBR or TME devices. Note the device locations and type on the floor plan.
Starting position for grid | Planning grid | Possible position of TBR/TME | Obstacle area | ||||
TBR | TME | SED |
|
|