Select Schedules from the Available Trees menu.
A list of schedules is displayed.
Select the Search button.
FIN Stack queries the database and returns a list of points that are schedulable but do not have a referenced schedule. These points display in the top section of the main window.
To assign returned points to a schedule, select and drag a tile to the Schedule heading in the bottom section of the main window. A badge appears, confirming the item or number of items that are selected; see an example in the screenshot below.
The schedule heading turns from light blue to medium blue. Release the mouse.
A warning window pops up, confirming the placement of the point in the schedule.
Select APPLY.
The points are removed from the schedulable list and assigned to the indicated schedule.