Pre-mounting:
- Check that the nozzle drilling is appropriate for the zone to be protected.
- Ensure that piping network supports are positioned so that the thrust cannot move the nozzle when the extinguishing agent is released.
To mount the nozzle on the piping:
- Clean the threads on the nozzle and on the pipe end.
- Apply an appropriate sealant to the nozzle thread.
- Screw the nozzle on the piping by hand.
- Tighten the nozzle using a 22 mm open-end wrench.
- For nozzles fitted with a cap, check that this cap can easily be ejected in case of a discharge.
Nozzle installation
Mount each nozzle at the location defined when the installation was designed.
Check that there are no obstacles in the path of the nozzle jets: ensure that there is sufficient room around the nozzle to guarantee effective discharge of the extinguishing agent.